- Name: Medan Municipal Transportation PPP Project
- Value: IDR 13,278 trillion
- GCA: Mayor of Medan
- Location: Medan
- Sector: Transportation, rail-based transportation sub-sector
- Status: Preparation, specifically the finalization of the project structure involving central government support

Medan Municipal Transportation Project aims to provide affordable, high-quality and sustainable mass transportation services to meet the demand for transprotation services in Medan city which is expected to experience significant congestion in 2024.
- Implementing Facility: pelaksana fasilitas yaitu PT SMI (Persero)
- Law Cosultant: ANG Law
- Financial Consultant: PT Deloitte Konsultan Indonesia
- Technical Consultant: Mot McDonnald
Indications of the scope of PPP: Design, Build, Finance, Operate and Maintaine, which specifically are:
- Providing rollong stock, operating and nurturting the LRT infrastructure;
- Build BRT infrastructure, provide BRT, and operate and maintain BRT facilities and infrastructure.
Consession Period: 30 years for LRT (including 4 years for construction). 32 years for BRT (including 2 years for construction)
- The project will be structured using the availability payment (AP) scheme
- Pra-qualification: Scheduled on Q1 of 2019
- RfP: Scheduled on Q2 of 2019
- Winner bidder announcement: scheduled on Q1 of 2020
- Contract signing: scheduled on Q1 of 2020
- Financial closes: scheduled on Q2 of 2020
- Construction: Scheduled on Q2 of 2020
- Operation: BRT on 2022 and LRT on 2024